Skip to main content
Qipu

Public contracts of Pont-Sainte-Maxence · 2022

Aménagement de la Place du Château Richard

Number 6 by amount of the 30 contracts Pont-Sainte-Maxence awarded in 2022.

Contract · Construction and Bâtiment · carried out in 60700

574k €
contract ceiling — what was paid on it is not published
Signed on 27 September 2022 · ended around February 2023 · 0.4 yrs
Ended26 Feb 2023

Who won it

VerdadSIREN 503561052

The competition

Number of bids not published for that year: the field is only systematic from 2024.

Adapted procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

View the consolidated DECP (data.gouv.fr) ↗

The form of the contract

PriceFerme et actualisable
Published amendments2

Other contracts of Verdad in Pont-Sainte-Maxence

Accord cadre multi attributaire avec marchés subséquents pour des travaux de voirie2025700k€Travaux de voirie, réseau pluvial, réseau eaux usées, et eau potable rue RAMON, bouleurs, bouchers a Pont-Sainte-Maxence2021720k€Aménagement de la Place du Château Richard2020574k€Aménagement de la Place du Château Richard2019540k€Travaux d’entretien voirie2019316k€

Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.

Source: Public procurement — DECP (data.gouv.fr)·Data·Method
Aménagement de la Place du Château Richard: 574 k€, Pont-Sainte-Maxence 2022 · Qipu