Skip to main content

Public contracts of Pontault-Combault · 2022 · Construction and buildings

Construction d’une école élémentaire et d’un restaurant scolaire à l’école Pablo Neruda

€295k
maximum contract amount over 13 months — what was paid on it is not published
Signed on 22 August 2022 · ended around September 2023 · 13 months

That is at most ~€272k a year on average: a maximum too.

Company selected

Sorbat 77Travaux de plâtrerie · registered office Saint-Fargeau-Ponthierry (77310) · headcount 20 to 49 employees · SIREN 421353079

The competition

87 bids received

awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 8 by amount of the 35 contracts Pontault-Combault published for 2022. It belongs to the policy Schools.

Contract details (procedure, price, amendments, lots)

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.