Skip to main content

Public contracts of Preuilly · 2026 · Construction and buildings

Protection/démolition/gros oeuvre

Mairie et salle des fêtes

€212k
maximum contract amount over 2 years — what was paid on it is not published
Signed on 25 March 2026 · running until about March 2028 · 2 yrs
Ongoing25 Mar 2028

That is at most ~€106k a year on average: a maximum too.

Company selected

Entreprise Contruction BâtimentTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Bourges (18000) · headcount 10 to 19 employees · SIREN 788192896
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.