Skip to main content

Public contracts of Quetigny · 2019 · Construction and buildings

Travaux de réalisation de la Maison de l’Enfant

Des lots

€14k
maximum contract amount over 8 months — what was paid on it is not published
Signed on 8 July 2019 · ended around March 2020 · 8 months

Company selected

SodifaluxFabrication d'appareils d'éclairage électrique · registered office Dijon (21000) · headcount 20 to 49 employees · SIREN 343728077

Number 13 by amount of the 18 contracts Quetigny published for 2019.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.