Travaux pour la construction de bâtiments neufs pour l’école élémentaire Charlie Chaplin et restaurant scolaire - Électricité courant fort/courant faible

Number 24 by amount of the 53 contracts Redon awarded in 2025.

Original label (DECP) : « Travaux pour la construction de bâtiments neufs pour l’école élémentaire Charlie Chaplin et restaurant scolaire - Électricité courant fort/courant faible » · Contract · Construction and Bâtiment · Travaux · carried out in 35 · environmental clauses

108k €
contract ceiling — what was paid on it is not published
Signed on 11 July 2025 · ended around May 2026 · 0.8 yrs
Ended11 May 2026

Who won it

Gergaud IndustrieSIREN 507387801

The competition

1 bid received

Adapted procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

View the consolidated DECP (data.gouv.fr) ↗

The form of the contract

PriceForfaitaire
Published amendments1
Subcontracting declaredno
Environmental considerationsCritère environnemental, Clause environnementale

Other contracts of Gergaud Industrie in Redon

Électricité courant fort / courant faible2024114k€Travaux pour la construction de bâtiments neufs pour l’école élémentaire Charlie Chaplin et restaurant scolaire - Centrale photovoltaïque202434k€Construction d’un local vélo sécurisé situé gare Sud avec prolongement en palissade devant le local Telecom SNCF et ravalement de ce dernier et d’un abri vélo gare Nord avec un bloc sanitaire et un…202211k€