Public contracts of Remire-Montjoly · 2025 · Construction and buildings

Groupe scolaire Ecquartier travaux de charpente couverture

€74k
maximum contract amount over 2 months — what was paid on it is not published
Signed on 17 July 2025 · ended around September 2025 · 2 months

Company selected

Guyane Bâtiment GénéraleTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Matoury (97351) · headcount 20 to 49 employees · SIREN 448558247

The competition

1 bid received

Median for this procedure in 2025: 3 bids, across 49692 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 31 by amount of the 47 contracts Remire-Montjoly published for 2025. It belongs to the policy Schools.

Other contracts of Guyane Bâtiment Générale in Remire-Montjoly

Groupe scolaire Ecoquartier2025 · maximum over 3 months220€kCharpente2025 · maximum over 6 months85€kCréation d’un kiosque zumba place publique2024 · maximum over 3 months100€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 1

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.