Elvina Lixef

€40k
maximum contract amount over 7 months — what was paid on it is not published
Signed on 9 July 2025 · ended around February 2026 · 7 months

Company selected

Global Costructions 973Autres travaux spécialisés de construction · registered office Matoury (97351) · SIREN 985354026

The competition

4 bids received

Median for this procedure in 2025: 3 bids, across 49692 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 47 by amount of the 47 contracts Remire-Montjoly published for 2025.

Other contracts of Global Costructions 973 in Remire-Montjoly

Place publique de Remire-Montjoly2025 · maximum over 3 months186€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 1

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.