Élémentaire moulin du comte

Création d’un ascenseur et d’un escalier · Travaux d’accessibilité et de sécurité incendie · Électricité

€19k
maximum contract amount over 7 months — what was paid on it is not published
Signed on 19 June 2025 · ended around January 2026 · 7 months

Company selected

Jolive ElecTravaux d'installation électrique dans tous locaux · registered office Chantepie (35135) · headcount 20 to 49 employees · SIREN 442519690

The competition

16 bids received

Median for this procedure in 2025: 3 bids, across 49692 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 174 by amount of the 210 contracts Rennes published for 2025. It belongs to the policy Schools.

Other contracts of Jolive Elec in Rennes

Construction neuve de la crèche municipale du Bois Perrin2026 · maximum over 16 months155€kGroupe scolaire Jean Zay2024 · maximum over 3 months13€kCollège Malifeu2023 · maximum over 3 months31€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 2

Subcontracting declared : no

Environmental considerations : Critère environnemental

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.