Public contracts of Retonfey · 2019 · Construction and buildings

Maîtrise d’oeuvre pour la restructuration de la mairie en maison communale à Retonfey

€126k
contract ceiling — what was paid on it is not published
Signed on 19 August 2019 · ended around August 2020 · 12 months

Who won it

Louvet Bureau d'Études TechniquesIngénierie, études techniques · registered office Nancy (54000) · headcount 6 to 9 employees · SIREN 393926761

Main holder, with the largest amount. The contract has 3 holders; the others are not shown here yet.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.