Skip to main content

Public contracts of Riedisheim · 2023 · Construction and buildings

Construction d’un accueil périscolaire sur le site de l’école Lyautey à Riedisheim

Ascenseurs

€41k
maximum contract amount over 16 months — what was paid on it is not published
Signed on 27 April 2023 · ended around August 2024 · 16 months

That is at most ~€30k a year on average: a maximum too.

Company selected

Orona EstAutres travaux d'installation n.c.a. · registered office Strasbourg (67200) · headcount 20 to 49 employees · SIREN 338508120

The competition

5 bids received

Median for this procedure in 2023: 3 bids, across 8316 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 44 by amount of the 55 contracts Riedisheim published for 2023. It belongs to the policy Schools.

Other contracts of Orona Est in Riedisheim

Projet de construction d’un nouveau complexe sportif (COSEC) à…2025 · maximum over 23 months39€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 1

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.