Skip to main content

Public contracts of Rieux · 2025 · Construction and buildings

Construction d’une maison de santé

Électricité

€90k
maximum contract amount over 14 months — what was paid on it is not published
Signed on 21 March 2025 · ended around May 2026 · 14 months

That is at most ~€77k a year on average: a maximum too.

Company selected

Lustr'Elec leTravaux d'installation électrique dans tous locaux · registered office Bruz (35170) · headcount 20 to 49 employees · SIREN 330220161

The competition

47 bids received

Median for this procedure in 2025: 3 bids, across 49692 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 6 by amount of the 17 contracts Rieux published for 2025.

Other contracts of Lustr'Elec le in Rieux

Construction d’une maison de santé lot 10 électricité-courant…2025 · maximum over 14 months90€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Environmental considerations : Critère environnemental