Public contracts of Riorges · 2023 · Construction and buildings

Charpente métallique

€75k
maximum contract amount over 7 months — what was paid on it is not published
Signed on 20 July 2023 · ended around February 2024 · 7 months

Company selected

Les Constructions Metalliques MontFabrication de structures métalliques et de parties de structures · registered office Briennon (42720) · headcount 10 to 19 employees · SIREN 406580126

Number 19 by amount of the 30 contracts Riorges published for 2023.

Other contracts of Les Constructions Metalliques Mont in Riorges

Construction et extension des locaux du service patrimoine et énergies…2022 · maximum over 8 months142€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.