Skip to main content

Public contracts of Rivesaltes · 2020 · Construction and buildings

Travaux d’accessibilité PMR

Écoles primaires et crèche halte garderie

€4k
maximum contract amount over 1 month — what was paid on it is not published
Signed on 28 October 2020 · ended around November 2020 · 1 month

Company selected

CO.RE.BATTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Thuir (66300) · headcount 10 to 19 employees · SIREN 804676682

Number 11 by amount of the 11 contracts Rivesaltes published for 2020. It belongs to the policy Schools.

Other contracts of CO.RE.BAT in Rivesaltes

Travaux2021 · maximum over 5 months40€kTravaux2021 · maximum over 5 months3€kTravaux2019 · maximum over 2 months29€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.