Public contracts of Rochefort · 2025
Extension du réseau de chaleur des Fourriers vers la zone de l’Arsenal et création de deux sous-stations
The largest contract Rochefort awarded in 2025, out of 36.
Contract · Construction and Bâtiment · Travaux · carried out in 17301 · social clauses · environmental clauses
1.2€M
contract ceiling — what was paid on it is not published
Who won it
DalkiaSIREN 456500537The competition
2 bids received
Adapted procedure · awarded to 3 companies
Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.
The form of the contract
PriceForfaitaire
Published amendments1
Subcontracting declaredyes
Social considerationsClause sociale
Environmental considerationsClause environnementale
The 2 lots
Lot 114 March 2025 · 2 bids622k€
Lot 214 March 2025 · 2 bids622k€
Other contracts of Dalkia in Rochefort
Extension du réseau de chaleur des Fourriers vers la zone de l’Arsenal et création de deux sous-stations2024622k€Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.