Public contracts of Rochefort-du-Gard · 2023 · Construction and buildings

Pistes de pump tracks de la Bergerie

€159k
maximum contract amount over 15 months — what was paid on it is not published
Signed on 9 May 2023 · ended around August 2024 · 15 months

That is at most ~€127k a year on average: a maximum too.

Company selected

PG Construction (PG Concept)Construction d'autres ouvrages de génie civil n.c.a. · registered office Tosse (40230) · SIREN 838501674

Number 4 by amount of the 18 contracts Rochefort-du-Gard published for 2023.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Mixte

Published amendments : 3

Subcontracting declared : yes

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.