Skip to main content

Public contracts of Rochetaillée-sur-Saône · 2021 · Construction and buildings

Complexe Multiactivité

€142k
contract ceiling — what was paid on it is not published
Signed on 4 October 2021 · ended around December 2022 · 14 months

Who won it

SM Bertholon ÉlectricitéTravaux d'installation électrique dans tous locaux · registered office Vindry-Sur-Turdine (69490) · headcount 6 to 9 employees · SIREN 305834459

Number 7 by amount of the 13 contracts Rochetaillée-sur-Saône published for 2021.

Other contracts of SM Bertholon Électricité in Rochetaillée-sur-Saône

Complexe multiactivité20212.7€M
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.