Skip to main content

Public contracts of Roncq · 2021 · Construction and buildings

Travaux de réhabilitation du centre musical

Bardage

€60k
maximum contract amount over 12 months — what was paid on it is not published
Signed on 25 October 2021 · ended around October 2022 · 12 months

Company selected

EcolopoConstruction de maisons individuelles · registered office La Madeleine (59110) · headcount 10 to 19 employees · SIREN 534738604

The competition

26 bids received

awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 12 by amount of the 37 contracts Roncq published for 2021.

Contract details (procedure, price, amendments, lots)

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.