Original label (DECP) : « Rénovation énergétique hôtel de ville - lot 4 - isolation thermique bardage - ac » · Contract · Construction and Bâtiment · Travaux · carried out in 63130

382k €
contract ceiling — what was paid on it is not published
Signed on 19 April 2024 · ended around December 2025 · 1.7 yrs
Ended19 Dec 2025

Who won it

Keser (SARL Keser)SIREN 409202157

The competition

Number of bids not published for that year: the field is only systematic from 2024.

Adapted procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

View the consolidated DECP (data.gouv.fr) ↗

The form of the contract

PriceMixte
Published amendments3
Subcontracting declaredyes

Other contracts of Keser (SARL Keser) in Royat

Rénovation énergétique hôtel de ville - lot 4 - isolation thermique bardage - ac2022734k€

Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.

Source: Public procurement — DECP (data.gouv.fr)·Data·Method