Travaux d’aménagement du giratoire joseph BEARD boulevard louis dagand a Rumilly.
Number 3 by amount of the 41 contracts Rumilly awarded in 2019.
Contract · Construction and Bâtiment · carried out in 74150
204k €
contract ceiling — what was paid on it is not published
Who won it
Eurovia AlpesSIREN 433888674The competition
Number of bids not published for that year: the field is only systematic from 2024.
Adapted procedure · awarded to 1 company
Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.
The form of the contract
PriceFerme et actualisable
Published amendmentsnone
The 2 lots
Lot 127 May 2019199k€
Lot 227 May 20195k€
Other contracts of Eurovia Alpes in Rumilly
Travaux revêtements bitumineux de voirie-bordures-caniveaux-équipements20263.2M€Lot 1 - Terrassements-revêtements de sols et bordures -ouvrages divers20252.4M€Lot 2 - Revêtements bitumineux - signalisation2025378k€Lot 1 - Terrassements-revêtements de sols et bordures -ouvrages divers202311.1M€Travaux revêtements bitumineux de voirie-bordures-caniveaux-équipements20233.2M€Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.