Skip to main content

Public contracts of Sablé-sur-Sarthe · 2020 · Construction and buildings

Ravalement, isolation du pignon et reprise rive

€17k
maximum contract amount over 2 months — what was paid on it is not published
Signed on 6 January 2020 · ended around March 2020 · 2 months

Company selected

S2MRéparation d'ouvrages en métaux · registered office Parce-Sur-Sarthe (72300) · headcount 10 to 19 employees · SIREN 453054710

Number 15 by amount of the 23 contracts Sablé-sur-Sarthe published for 2020.

Other contracts of S2M in Sablé-sur-Sarthe

Démolition et reconstruction d’un WC Public2020 · maximum over 5 months4€kAménagement du hangar des écuries en atelier2018 · maximum over 3 months3€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.