Skip to main content

Public contracts of Sabran · 2023 · Energy

Rénovation énergétique éclairage public

€41k
maximum contract amount over 4 years — what was paid on it is not published
Signed on 29 December 2023 · running until about December 2027 · 4 yrs
Ongoing29 Dec 2027

That is at most ~€10k a year on average: a maximum too.

Company selected

Entreprise de Travaux ElectriquesConstruction de réseaux électriques et de télécommunications · registered office Ales (30100) · headcount 20 to 49 employees · SIREN 307020347

Number 3 by amount of the 3 contracts Sabran published for 2023.

Other contracts of Entreprise de Travaux Electriques in Sabran

Rénovation énergétique éclairage public Hameau de Donnat2023 · maximum over 4 years51€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.