Skip to main content
Qipu

Public contracts of Sada · 2023

Extention Ecole maternelle Sada 2 -Travaux supplémentaires

Number 31 by amount of the 34 contracts Sada awarded in 2023.

Contract · Construction and Bâtiment · carried out in 97640

46k €
contract ceiling — what was paid on it is not published
Signed on 14 August 2023 · ended around September 2023 · 0.1 yrs
Ended13 Sept 2023

Who won it

EliteSIREN 830326500

The competition

Number of bids not published for that year: the field is only systematic from 2024.

Adapted procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

View the consolidated DECP (data.gouv.fr) ↗

The form of the contract

PriceFerme
Published amendmentsnone

Other contracts of Elite in Sada

Travaux de raccordement électriques202589k€Construction d’un parking lot no3 Eclairage Public -Extention Ecole maternelle Sada 2202293k€Travaux de rénovation de l’école maternelle de Mangajou lot no 8 Electricité202265k€Extension de l’école maternelle Sada II- Sada2019110k€Travaux de construction d’un réfectoire et 2 salles de classe à l’école élémentaire de Mangajou (lot no5 Electricité)201981k€

Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.

Source: Public procurement — DECP (data.gouv.fr)·Data·Method
Extention Ecole maternelle Sada 2 -Travaux supplémentaires: 46 k€, Sada 2023 · Qipu