Public contracts of Saint-Amand-Montrond · 2020 · Construction and buildings

Aménagement de l’espace restauration scolaire à l’École Mallard

€15k
maximum contract amount over 7 months — what was paid on it is not published
Signed on 16 March 2020 · ended around October 2020 · 7 months

Company selected

Menuiseries Bois MetalTravaux de menuiserie bois et PVC · registered office Moulins (03000) · headcount 10 to 19 employees · SIREN 492057567

Number 17 by amount of the 19 contracts Saint-Amand-Montrond published for 2020. It belongs to the policy Schools.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.