Skip to main content

Public contracts of Saint-Avertin · 2025 · Construction and buildings

Déploiement du réseau très haut débit en fibre optique noire

€110k
framework agreement: a maximum envelope for orders over 4 years, not spending — what was paid on it is not published
Signed on 28 July 2025 · running until about July 2029 · 4 yrs
Ongoing28 Jul 2029

That is at most ~€28k a year on average: a maximum too.

Company selected

Eiffage Énergie Systèmes - Réseau MobileTravaux d'installation électrique dans tous locaux · registered office Marseille (13002) · headcount 500 to 999 employees · SIREN 879916799

Number 11 by amount of the 23 contracts Saint-Avertin published for 2025.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Forfaitaire

Published amendments : 2

Subcontracting declared : yes

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.