Le projet concerne les travaux de réhabilitation et extension de l’école de Cesson Bourg à Saint-Brieuc à l’intérieur des locaux…

Terrassement /…

€134k
maximum contract amount over 2 years — what was paid on it is not published
Signed on 28 August 2023 · ended around September 2025 · 2 yrs

That is at most ~€64k a year on average: a maximum too.

Company selected

Paillardon T.P.Travaux de terrassement courants et travaux préparatoires · registered office Tregueux (22950) · headcount 20 to 49 employees · SIREN 344986963

The competition

25 bids received

Median for this procedure in 2023: 3 bids, across 8324 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 22 by amount of the 69 contracts Saint-Brieuc published for 2023. It belongs to the policy Schools.

Other contracts of Paillardon T.P. in Saint-Brieuc

Travaux de mise en sécurité de l’ouvrage hydraulique de Douvenant2024 · maximum over 7 months110€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 3

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.