Skip to main content

Public contracts of Saint-Brieuc · 2023 · Construction and buildings

Le projet concerne les travaux de réhabilitation et extension de l’école de Cesson Bourg à Saint-Brieuc à l’intérieur des locaux…

Électricité…

€256k
maximum contract amount over 2 years — what was paid on it is not published
Signed on 28 August 2023 · ended around September 2025 · 2 yrs

That is at most ~€123k a year on average: a maximum too.

Company selected

Le Bohec Armor ÉlectricitéTravaux d'installation électrique dans tous locaux · registered office Tremuson (22440) · headcount 10 to 19 employees · SIREN 535163356

The competition

25 bids received

Median for this procedure in 2023: 3 bids, across 8316 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 13 by amount of the 69 contracts Saint-Brieuc published for 2023. It belongs to the policy Schools.

Other contracts of Le Bohec Armor Électricité in Saint-Brieuc

Programme de travaux portant sur l’installation d’une cuisine au RDC…2025 · maximum over 15 months100€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 2

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.