Skip to main content

Public contracts of Saint-Claude · 2022 · Construction and buildings

Démolition et reconstruction d’un ouvrage d’art, avec passerelle provisoire et itinéraire alternatif

€618k
maximum contract amount over 10 months — what was paid on it is not published
Signed on 8 July 2022 · ended around May 2023 · 10 months

Company selected

Parutto SASTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Miribel (01700) · headcount 20 to 49 employees · SIREN 763201092

Number 3 by amount of the 13 contracts Saint-Claude published for 2022.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.