Public contracts of Saint-Colomban · 2026 · Construction and buildings

Charpente bois

€51k
contract ceiling — what was paid on it is not published
Signed on 24 June 2026 · running until about December 2027 · 18 months
Ongoing24 Dec 2027

Who won it

BoisborealFabrication de charpentes et d'autres menuiseries · registered office Coex (85220) · headcount 20 to 49 employees · SIREN 882199565

The competition

4 bids received

Median for this procedure in 2026: 3 bids, across 34631 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 12 by amount of the 12 contracts Saint-Colomban published for 2026.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 1

Environmental considerations : Clause environnementale, Critère environnemental

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.