Public contracts of Saint-Domineuc · 2020 · Other

Réaménagement du pôle sportif henri nogues

Électricité courants forts/faibles

€49k
maximum contract amount over 8 months — what was paid on it is not published
Signed on 19 June 2020 · ended around February 2021 · 8 months

Company selected

Ruauld ÉlectricitéTravaux d'installation électrique dans tous locaux · registered office Poilley (50220) · headcount 20 to 49 employees · SIREN 523558195

Number 8 by amount of the 8 contracts Saint-Domineuc published for 2020.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none