Public contracts of Saint-Donat-sur-l'Herbasse · 2019 · Construction and buildings

Construction d’un bâtiment scolaire

École Louis Aragon: · Enduit

€16k
maximum contract amount over 11 months — what was paid on it is not published
Signed on 23 July 2019 · ended around June 2020 · 11 months

Company selected

Ordek FacadesAutres travaux de finition · registered office Salaise-Sur-Sanne (38150) · headcount 6 to 9 employees · SIREN 500315270

Number 15 by amount of the 16 contracts Saint-Donat-sur-l'Herbasse published for 2019. It belongs to the policy Schools.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.