Public contracts of Saint-Égrève · 2024 · Professional services

Maîtrise d’oeuvre pour la restructuration et l’extension du restaurant scolaire prédieu

€112k
maximum contract amount over 11 months — what was paid on it is not published
Signed on 28 November 2024 · ended around October 2025 · 11 months

Company selected

Société Rhone Alpes d'Études Techniques de la Construction - Sor AetecIngénierie, études techniques · registered office Echirolles (38130) · headcount 20 to 49 employees · SIREN 327851564

A contract awarded to a consortium of 5 holders; above, the main holder. With it: Rez'On, CCG, Studis Ingenierie, Onirik Architectes. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

13 bids received

Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 5 companies

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 24 by amount of the 67 contracts Saint-Égrève published for 2024.

Other contracts of Société Rhone Alpes d'Études Techniques de la Construction - Sor Aetec in Saint-Égrève

Maîtrise d’oeuvre pour la rénovation2024 · maximum over 12 months140€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none