Public contracts of Saint-Florent-sur-Cher · 2025 · Construction and buildings

Rénovation de l’école maternelle Rive droite

€45k
maximum contract amount over 7 months — what was paid on it is not published
Signed on 11 March 2025 · ended around October 2025 · 7 months

Company selected

Se d'Électricité et de ChauffageTravaux d'installation d'équipements thermiques et de climatisation · registered office Bourges (18000) · headcount 20 to 49 employees · SIREN 501441711

The competition

2 bids received

Median for this procedure in 2025: 3 bids, across 49692 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 12 by amount of the 18 contracts Saint-Florent-sur-Cher published for 2025. It belongs to the policy Schools.

Other contracts of Se d'Électricité et de Chauffage in Saint-Florent-sur-Cher

Travaux de rénovation de l’école maternelle Rive Droite2025 · maximum over 7 months45€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.