Skip to main content

Public contracts of Saint-Gilles · 2021 · Construction and buildings

Réaménagement de l’accueil de la Mairie

Façades

€17k
maximum contract amount over 3 years — what was paid on it is not published
Signed on 25 November 2021 · ended around November 2024 · 3 yrs

That is at most ~€6k a year on average: a maximum too.

Company selected

Saint Genies Bâtiment Facades - SGBFTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Saint-Genies-De-Malgoires (30190) · headcount 10 to 19 employees · SIREN 533835260

Number 66 by amount of the 78 contracts Saint-Gilles published for 2021.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.