Public contracts of Saint-Herblain · 2019 · Construction and buildings

Opération de construction et de réhabilitation du complexe sportif tennis de l’Orvasserie à Saint-Herblain

Du · Cloisons / Isolations / Faux-plafonds

€33k
maximum contract amount over 15 months — what was paid on it is not published
Signed on 22 February 2019 · ended around May 2020 · 15 months

That is at most ~€26k a year on average: a maximum too.

Company selected

Aménagement Decoration Isolation AdiAutres travaux de finition · registered office Saint-Herblain (44800) · headcount 10 to 19 employees · SIREN 424636181

Number 108 by amount of the 140 contracts Saint-Herblain published for 2019. It belongs to the policy Culture, sport and youth.

Other contracts of Aménagement Decoration Isolation Adi in Saint-Herblain

Travaux accessibilité2023 · maximum over 21 months66€kChangetterie-Cloisons / Isolations / Faux Plafond2019 · maximum over 14 months24€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.