Public contracts of Saint-Hilaire-de-Brethmas · 2026 · Construction and buildings

Génie civil et voirie et réseaux divers

€444k
maximum contract amount over 12 months — what was paid on it is not published
Signed on 29 May 2026 · running until about May 2027 · 12 months
Ongoing29 May 2027

Company selected

Marron B.T.P.Construction d'ouvrages d'art · registered office Ales (30100) · headcount 10 to 19 employees · SIREN 508356490

The largest of the 2 contracts Saint-Hilaire-de-Brethmas published for 2026.

Other contracts of Marron B.T.P. in Saint-Hilaire-de-Brethmas

Reprise de la cour oasis2025 · maximum over 1 month49€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.