Public contracts of Saint-Ismier · 2024 · Construction and buildings

Travaux d’éclairage public

€200k
framework agreement: a maximum envelope for orders over 18 months, not spending — what was paid on it is not published
Signed on 2 April 2024 · ended around October 2025 · 18 months

That is at most ~€133k a year on average: a maximum too.

Company selected

GreenalpDistribution d'électricité · registered office Grenoble (38000) · headcount 200 to 249 employees · SIREN 833619109

The competition

4 bids received

Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 12 by amount of the 38 contracts Saint-Ismier published for 2024. It belongs to the policy Town planning and housing.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Unitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.