Skip to main content

Public contracts of Saint-Jean-de-Luz · 2025 · Energy

Réhabilitation de l’éclairage public au centre-ville

€1.4M
framework agreement: a maximum envelope for orders over 4 years, not spending — what was paid on it is not published
Signed on 29 December 2025 · running until about December 2029 · 4 yrs
Ongoing29 Dec 2029

That is at most ~€350k a year on average: a maximum too.

Company selected

Spie CitynetworksConstruction de réseaux électriques et de télécommunications · registered office Saint-Ouen-Sur-Seine (93400) · headcount 2,000 to 4,999 employees · SIREN 434085395

The competition

6 bids received

Median for this procedure in 2025: 3 bids, across 49692 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Amounts paid

Electricity, gas and heating: €824k paid by Saint-Jean-de-Luz in 2025, all suppliers together (its accounts). The accounts do not say what share went to Spie Citynetworks.

Number 2 by amount of the 49 contracts Saint-Jean-de-Luz published for 2025. It belongs to the policy Town planning and housing.

Other contracts of Spie Citynetworks in Saint-Jean-de-Luz

Réhabilitation de l’éclairage public au centre-ville2025 · maximum over 4 years350€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Forfaitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.