Skip to main content

Public contracts of Saint-Jean-Saint-Nicolas · 2021 · Construction and buildings

Mise en place d’une citerne incendie au hameau de clot Davin

€22k
maximum contract amount over 3 months — what was paid on it is not published
Signed on 31 August 2021 · ended around November 2021 · 3 months

Company selected

Andre TPTravaux de terrassement courants et travaux préparatoires · registered office La Rochette (05000) · headcount 20 to 49 employees · SIREN 400925640

Number 5 by amount of the 5 contracts Saint-Jean-Saint-Nicolas published for 2021.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.