Public contracts of Saint-Jory · 2019 · Construction and buildings

Agrandissement de l’école du Lac : hors d’eau, hors d’air

€489k
maximum contract amount over 12 months — what was paid on it is not published
Signed on 16 October 2019 · ended around October 2020 · 12 months

Company selected

Scobat Société Construction BâtimentConstruction d'autres bâtiments · registered office Saint-Jory (31790) · SIREN 539264549

Number 3 by amount of the 11 contracts Saint-Jory published for 2019.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.