Public contracts of Saint-Laurent-de-Neste · 2023 · Construction and buildings

Pompe à chaleur pour l’école

€108k
maximum contract amount over 3 months — what was paid on it is not published
Signed on 7 July 2023 · ended around October 2023 · 3 months

Company selected

SARL EnergecoIngénierie, études techniques · registered office Pau (64000) · headcount 10 to 19 employees · SIREN 377716725

Number 3 by amount of the 3 contracts Saint-Laurent-de-Neste published for 2023.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.