Skip to main content

Public contracts of Saint-Laurent-du-Maroni · 2019 · Construction and buildings

Mise en accessibilité des établissements scolaires de la commune de Saint-Laurent-du-Maroni

€112k
maximum contract amount over 4 months — what was paid on it is not published
Signed on 8 January 2019 · ended around May 2019 · 4 months

Company selected

Trapeze IngenierieIngénierie, études techniques · registered office Saint-Laurent-Du-Maroni (97320) · SIREN 811088731

Number 23 by amount of the 100 contracts Saint-Laurent-du-Maroni published for 2019. It belongs to the policy Schools.

Other contracts of Trapeze Ingenierie in Saint-Laurent-du-Maroni

Travaux de remplacement d’huisseries dans les établissements scolaires…2019 · maximum over 2 years45€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.