Skip to main content

Public contracts of Saint-Maixent-l'École · 2023 · Construction and buildings

Travaux de confortement provisoire du bâtiment 36 rue chalon

€75k
maximum contract amount over 6 months — what was paid on it is not published
Signed on 17 July 2023 · ended around January 2024 · 6 months

Company selected

Ste de Travaux Publics du MelloisConstruction de réseaux pour fluides · registered office Melle (79500) · headcount 20 to 49 employees · SIREN 332749886

Number 10 by amount of the 18 contracts Saint-Maixent-l'École published for 2023. It belongs to the policy Streets and transport.

Other contracts of Ste de Travaux Publics du Mellois in Saint-Maixent-l'École

Maison de santé : gros œuvre et démolition2025 · maximum over 13 months664€kVoirie réseaux divers-Espaces Verts2025 · maximum over 5 months62€kRéhabilitation du centre technique municipal : gros œuvre, voirie…2022 · maximum over 5 years360€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.