Rue de la Riaille

€285k
maximum contract amount over 18 months — what was paid on it is not published
Signed on 4 April 2024 · ended around October 2025 · 18 months

That is at most ~€190k a year on average: a maximum too.

Company selected

Astier TPTravaux de terrassement courants et travaux préparatoires · registered office Saint-Marcel-D'Ardeche (07700) · headcount 6 to 9 employees · SIREN 813534617

The competition

2 bids received

Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Other contracts of Astier TP in Saint-Marcel-d'Ardèche

Centre de santé2026 · maximum over 13 months121€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.