Skip to main content

Public contracts of Saint-Nicolas-de-Bourgueil · 2023 · Construction and buildings

Maîtrise d’œuvre pour la reconstruction de l’église après la tornade du 19 juin 2021

€149k
maximum contract amount over 4 months — what was paid on it is not published
Signed on 30 May 2023 · ended around September 2023 · 4 months

Who won it

Saboureau IngenierieActivité des économistes de la construction · registered office Tours (37100) · headcount 3 to 5 employees · SIREN 408128072

A contract awarded to 3 holders; above, the main holder. With it: Moreau Boktor Architectes, Le Be Associes. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The largest of the 3 contracts Saint-Nicolas-de-Bourgueil published for 2023.

Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.