École primaire bellemene VRD aménagement ext

Number 2 by amount of the 84 contracts Saint-Paul awarded in 2018.

Contract · Construction and Bâtiment · carried out in 97460

3.4€M
contract ceiling — what was paid on it is not published
Signed on 19 July 2018 · ended around July 2021 · 3.0 yrs
Ended19 Jul 2021

Who won it

Bureau D'Études Techniques Conception et Realisation (Betcr)SIREN 802809343

The competition

Number of bids not published for that year: the field is only systematic from 2024.

Procédure négociée avec mise en concurrence préalable · awarded to 2 companies

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

View the consolidated DECP (data.gouv.fr) ↗

The form of the contract

PriceRévisable
Published amendmentsnone

The 2 lots

Lot 119 July 20181.7M€
Lot 219 July 20181.7M€

Other contracts of Bureau D'Études Techniques Conception et Realisation (Betcr) in Saint-Paul

Reconstruction école primaire grand fond lot01b VRD20251.2M€Reconstruction école primaire grand fond lot 00a VRD clôtures2024612k€Aménagement du chemin tamatave saint gilles les hauts20231.2M€Reconstruction école primaire grand fond lot01b VRD20231M€Fournitures et pose équipements signalisation directionnelle2023800k€

Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.

Source: Public procurement — DECP (data.gouv.fr)·Data·Method