Public contracts of Saint-Pierre · 2024 · Construction and buildings

Réhabilitation de l’église saint-augustin

€96k
maximum contract amount over 2.5 years — what was paid on it is not published
Signed on 24 June 2024 · running until about December 2026 · 2.5 yrs
Ongoing24 Dec 2026

That is at most ~€39k a year on average: a maximum too.

Who won it

Herve ThermiqueTravaux d'installation d'équipements thermiques et de climatisation · registered office Joue-Les-Tours (37300) · headcount 2,000 to 4,999 employees · SIREN 627220049

The competition

4 bids received

Median for this procedure in 2024: 3 bids, across 48385 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 127 by amount of the 246 contracts Saint-Pierre published for 2024. It belongs to the policy Culture, sport and youth.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 1

Subcontracting declared : no

Environmental considerations : Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.