Skip to main content

Public contracts of Saint-Pol-de-Léon · 2025 · Professional services

Maîtrise d’oeuvre pour la création d’un accueil de loisirs dans l’enceinte du groupe scolaire Jean Jaurès et Pierre et Marie Curie à Saint-Pol-de-Léon

€90k
maximum contract amount over 22 months — what was paid on it is not published
Signed on 13 October 2025 · running until about August 2027 · 22 months
Ongoing14 Aug 2027

That is at most ~€49k a year on average: a maximum too.

Company selected

Ecmo IngenierieIngénierie, études techniques · registered office Guipavas (29490) · headcount 3 to 5 employees · SIREN 537539231

A contract awarded to 2 holders; above, the main holder. With it: Collectif Architectes Leopold Cante - Calc. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

1 bid received

Median for this procedure in 2025: 1 bid, across 3432 comparable contracts. Contract awarded without prior advertising or competitive bidding · awarded to 2 companies

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 8 by amount of the 12 contracts Saint-Pol-de-Léon published for 2025.

Other contracts of Ecmo Ingenierie in Saint-Pol-de-Léon

Suivi de chantier de construction du padel sur la commune de…2026 · maximum over 2.5 years43€k
Contract details (procedure, price, amendments, lots)

Procedure : Marché passé sans publicité ni mise en concurrence préalable

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.