Skip to main content

Public contracts of Saint-Priest · 2024 · Construction and buildings

Travaux neufs divers de génie civil pour éclairage public

€500k
framework agreement: a maximum envelope for orders over 4 years, not spending — what was paid on it is not published
Signed on 30 October 2024 · running until about October 2028 · 4 yrs
Ongoing30 Oct 2028

That is at most ~€125k a year on average: a maximum too.

Company selected

Entreprise CoiroTravaux de terrassement courants et travaux préparatoires · registered office Saint-Priest (69800) · headcount 100 to 199 employees · SIREN 959502139

The competition

2 bids received

Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 17 by amount of the 75 contracts Saint-Priest published for 2024. It belongs to the policy Town planning and housing.

Other contracts of Entreprise Coiro in Saint-Priest

Raccordement de 5 bâtiments communaux au réseau de chaleur urbain de la…2026 · maximum over 3 months41€kTravaux neufs divers de génie civil pour l’éclairage public2024 · maximum over 4 years500€kTravaux neufs d’éclairage public génie civil2020 · maximum over 4 years900€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Unitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.