Skip to main content

Public contracts of Saint-Priest · 2026 · Construction and buildings

Travaux réfection toiture et isolation des combles du CTM

€54k
maximum contract amount over 2 months — what was paid on it is not published
Signed on 4 March 2026 · ended around May 2026 · 2 months

Company selected

Ecrin Auvergne Rhone Alpes (B.V.S.)Autres travaux spécialisés de construction · registered office Venissieux (69200) · headcount 20 to 49 employees · SIREN 808010094

The competition

7 bids received

Median for this procedure in 2026: 3 bids, across 23525 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 61 by amount of the 81 contracts Saint-Priest published for 2026.

Other contracts of Ecrin Auvergne Rhone Alpes (B.V.S.) in Saint-Priest

Travaux de réfection d’une partie de la toiture…2026 · maximum over 2 months45€kTravaux entretien et réparation toitures terrasses gouttiere2025 · maximum over 3.5 years800€kTravaux d’entretien et de réparation des toitures, terrasses…2025 · maximum over 3 years800€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 2

Subcontracting declared : yes

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.