Public contracts of Saint-Priest · 2026 · Construction and buildings

Rénovation, entretien et réparation des bâtiments

€800k
framework agreement: a maximum envelope for orders over 4 years, not spending — what was paid on it is not published
Signed on 4 March 2026 · running until about March 2030 · 4 yrs
Ongoing4 Mar 2030

That is at most ~€200k a year on average: a maximum too.

Company selected

Spie Batignolles ÉnergieTravaux d'installation électrique dans tous locaux · registered office Nanterre (92000) · headcount 500 to 999 employees · SIREN 552119760

The competition

15 bids received

Median for this procedure in 2026: 3 bids, across 23525 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 7 by amount of the 81 contracts Saint-Priest published for 2026.

Other contracts of Spie Batignolles Énergie in Saint-Priest

Rénovation, entretien et réparation des bâtiments2026 · maximum over 4 years800€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Unitaire

Published amendments : none

Environmental considerations : Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.